Given the list of activities, the expected time estimates, and

Question : Given the list of activities, the expected time estimates, and : 2418

Given the list of activities, the expected time estimates, and variances, compute the probability that the project time will be less than 30 minutes. Round Z to two decimals

Activity Te minutes) Variance 0.5 2.00 1.75 6.17 8.34 1.45 10.05 3.00