c) based the calculation of the estimated times, the critical

Question : c) based the calculation of the estimated times, the critical : 3191

c) based on the calculation of the estimated times, the critical path is

d) the estimated time for the critical path is (in weeks)

e) the activity variance along the critical path is (in weeks)

f) the probability that Hopkins Hospitality will finish the project in 40 weeks or less

Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels. Time (weeks) Time (weeks) Immediate Immediate Activity a m b Predecessor(s Activity b Predecessor(s) C. E 9 10 23 14 16 D, G, H 10 14 I, J C, E 20 a) The expected (estimated) time for activity C is 13.33 weeks. (Round your response to two decimal places b) The variance for activity C is 1.78 weeks. (Round your response to two decimal places) c) Based on the calculation of the estimated times, the critical path is

Solution
5 (1 Ratings )

Solved
Statistics 11 Months Ago 151 Views
This Question has Been Answered!
Unlimited Access
Explore More than 2 Million+
  • Textbook Solutions
  • Flashcards
  • Homework Answers
  • Documents
Signup for Instant Access!
Ask an Expert
Our Experts can answer your tough homework and study questions
41036 Statistics Questions Answered!
Post a Question