91.A(n)_____ the original project plan plus approved changes. 92.The ratio of

Question : 91.A(n)_____ the original project plan plus approved changes. 92.The ratio of : 1525110

 

 

91.A(n)_____ is the original project plan plus approved changes.

92.The ratio of actual work completed to the percentage of work planned to have been completed at any given time during the life of the project or activity is known as the _____.

93.The _____ is the portion of the approved total cost estimate planned to be spent on an activity during a given period.

94.The total direct and indirect costs incurred in accomplishing work on an activity during a given period is known as the _____.

95.The _____ is based on the original planned costs for the project or activity and the rate at which the team is completing work on the project or activity to date.

96.The _____ index is the ratio of earned value to planned value.

97.The cost performance index can be used to calculate the _____ which gives an approximate cost of completing a project based on performance to date.

 

 

Solution
5 (1 Ratings )

Solved
Computer Science 1 Year Ago 10 Views
This Question has Been Answered!
Unlimited Access Free
Explore More than 2 Million+
  • Textbook Solutions
  • Flashcards
  • Homework Answers
  • Documents
Signup for Instant Access!
Ask an Expert
Our Experts can answer your tough homework and study questions
154049 Computer Science Questions Answered!
Post a Question