Question :
6) The document which contains the specifications of what needed : 2065982
6) The document which contains the specifications of what is needed and details the information that must be submitted by a supplier is known as
A) request for quotation.
B) bid specification.
C) preferred supplier contractor.
D) statement of work.
7) A survey administered to suppliers to determine fit with purchaser needs is known as
A) request for quotation.
B) request for proposal.
C) preferred supplier contractor.
D) supplier self-assessment.
8) Being aware of cultural nuances should occur during which step of the negotiation process?
A) Preparation
B) Face-to-face discussions
C) Debriefing
D) None of the above
9) Self-assessment to provide accurate and timely feedback during the negotiating team should occur during which step of the negotiation process?
A) Preparation
B) Face-to-face discussions
C) Debriefing
D) None of the above
10) The multi-criteria decision making method often used for supplier evaluation and selection is known as ________.