2.  If the time remaining to complete a job 10

Question : 2.  If the time remaining to complete a job 10 : 2416

2.  If the time remaining to complete a job is 10 days and the lead time remaining is 12 days, what is the critical ratio? Is the order ahead of schedule, on schedule, or behind schedule? Explain your answer.